Ever wonder why Rowell's still has a fence across it every time you drive past MM 104.5 bayside? The second phase of work stalled, the county reworked the design, and the plan that came out of that redesign includes something Key Largo has been missing: a fenced dog park.
Monroe County closed Rowell's Waterfront Park on Sept. 21 "until further notice" for Phase 2 work and said it expects the project to be done in December. When the gate opens, though, the park still won't be finished. A third phase is already funded and is set to start in early 2027. The bayside green is changing in stages, and this closure is the stage that adds the most for anyone with a dog.
This is the second closure of the season. In August, Keys Weekly reported that the park had closed through Sept. 1. County parks and beaches director John Allen told the paper, "Due to unexpected delays, the project has taken longer than originally anticipated."
That same story explains what happened. According to the county, Phase 2 construction stopped after an issue came up that forced a redesign. While the redesign was underway, the county won additional grant money, so project management and parks and beaches folded in improvements that weren't in the original plan. The September notice then replaced the Sept. 1 date with a longer closure and the December target. The extra months behind the fence are what made room for the new features.
The plan for Phase 2 has been rewritten more than once in four years. Keys Weekly covered it in March 2022, in October 2025 and again in August 2026, and putting those descriptions side by side shows where the dog park came from.
| When Keys Weekly described it | What Phase 2 was supposed to include |
|---|---|
| March 2022, when the state grant was announced | More parking, restrooms, shared-use paths, lighting, electricity and Wi-Fi |
| October 2025 | Field regrading and resodding, sidewalks, a lower-lot renovation, lighting, paths and drainage, at $2.9 million |
| August 2026, after the redesign | A fenced dog park, new field and park lighting, upgraded turf on the multiuse field, an expanded parking lot, dog water stations, picnic tables, trash receptacles and other amenities |
The dog park and the dog water stations appear only in the 2026 version. Lighting and parking have been in the plan from the start, which makes sense for a park that hosts evening events and fills up on holidays.
Money for this phase comes from a Community Development Block Grant. The Florida Keys Free Press via KeysNews reported the grant at $2,956,533 with no county match, and said the construction contract was negotiated to just under the grant ceiling. In other words, Phase 2 uses close to every dollar available, without drawing on the county budget.
Even once Phase 2 wraps up, some of the features people picture for a waterfront park still won't be there. According to Keys Weekly, Phase 3 is the final phase and will bring:
The county expects Phase 3 construction to start in early 2027, and it is fully funded by a Tourist Development Council brick-and-mortar grant. That means the park you get back this winter will have new lights, turf, parking and a place for dogs to run off-leash, and shade and a playground will come later.
It helps to remember how long this has been in the works. As Keys Weekly reported in 2022, the Board of County Commissioners bought the old Rowell's Marina in December 2013 to turn it into a public park. Littlejohn Engineering Associates started design in December 2016, and conceptual plans went before the public in April 2019. According to the same story, Phase 1 delivered a restroom, a small parking lot, a realigned entrance and a deceleration lane off the Overseas Highway. Charley Toppino & Sons built it for about $1.4 million, with $500,000 from the Tourist Development Council and $900,000 from the county. Minutes from the county Parks and Recreation Advisory Board in March 2023 list Phase 1 as complete.
The 2022 coverage had one more detail that still comes up in conversation. The master plan includes a pay station for charging non-residents, but it wasn't part of any scheduled construction phase, and county officials said the park would stay free for locals. None of the 2026 descriptions of Phase 2 or Phase 3 mention a pay booth.
Rowell's isn't just open grass. The county's facility listing includes a kayak launch, leashed pets, a mobility mat, picnic areas, restrooms and water access. Over the years it has hosted the Buccaneer Blast Regatta, Fourth of July festivities and the Key Largo Bridge Run.
The 2026 Buccaneer Blast was held at Rowell's on April 18 and 19, well before this closure. The Florida Keys tourism office lists the annual Blackwater Sound fireworks at Rowell's and the Key Largo July 4 parade finishing at Key Largo Community Park. The new field lighting and bigger parking lot in Phase 2 are the pieces those big gatherings put to work.
For now, dog walks and paddle launches have to happen somewhere else. Here's what's nearby, based on how each place lists itself:
Fair warning: none of these stops has a fenced off-leash area. That's what makes the Rowell's dog park the biggest change in this phase, and why the December target matters so much to dog owners in the Upper Keys.
The county's official word is still a December finish, and construction schedules in the Keys tend to slip. The county posted this closure on its Monroe County news flash page and said signs would be posted at each affected park.
I'm Kelly Randin with kelly randin, and I've watched Rowell's go from an old marina to the park it's becoming. If you're wondering how projects like this one or Phase 3 might affect your corner of Key Largo, or you just want to swap tips on where your dog can stretch its legs this fall, I'm happy to talk. Let's Connect.
Stay up to date on the latest real estate trends.